Home/VIC/Section 173 Agreement

Section 173 agreements, explained

A contract between a council and a landowner, recorded on the title so that it binds every owner who comes after. If your title mentions one, this is what it means.

Why this matters in Victoria

The obligation isn’t on the title — it’s in the agreement

A Register Search Statement lists the agreement and gives its dealing number. It does not reproduce what was agreed. Whether the land can be subdivided again, whether a second dwelling is permitted, whether you have inherited an obligation to maintain something — all of that is in the agreement document, which is ordered separately. A title search on its own is not enough before buying or designing.

What a Section 173 agreement contains

  • Who it binds
    The owner who signed it and, because it is recorded on the title, every owner after them. You can be bound by an agreement entered into decades before you bought.
  • What the owner has promised to do, or not do
    The substance. Common ones: no further subdivision, a limit on the number of dwellings, maintaining landscaping or a wastewater system, restricting use of an outbuilding, contributing to infrastructure, keeping a dwelling as a single occupancy.
  • The land it applies to
    Sometimes the whole parcel, sometimes a defined part of it. Where land has been subdivided since, working out which of today's lots carry the burden is its own exercise.
  • When and how it ends
    Some agreements end on a stated event — the completion of works, a date, the issue of a statement of compliance. Many have no end date at all and run until they are formally ended.

Why they appear

As a permit condition
The commonest reason by far. A permit is granted on the basis that something is guaranteed beyond the life of the permit, and an agreement is how the council makes that promise run with the land rather than with the applicant.
To secure a planning outcome the scheme cannot
A planning scheme controls what may be approved. It cannot easily compel an owner to maintain something, pay for something later, or refrain from an otherwise-permitted use. An agreement can.
In rural and environmental settings
Limits on further dwellings, revegetation, bushfire management, effluent systems and dam maintenance all appear in s173 agreements on rural land.
Development contributions and affordable housing
Where a contribution is agreed rather than levied, the agreement is the mechanism that records it.

Questions

What is a Section 173 agreement?
An agreement between a council (as responsible authority) and a landowner, made under section 173 of the Planning and Environment Act 1987. Once recorded on the title it binds not just the owner who signed it but everyone who owns the land afterwards. In practice it is a planning condition given permanent effect.
How do I know if my property has one?
It is recorded on the title as an agreement, with its dealing number. The title names it; it does not reproduce it. To know what you have actually agreed to, you need a copy of the agreement itself, which is ordered as a separate document using that dealing number.
The title mentions one. Why can't I read it there?
Because a title is an index, not a library. It tells you an agreement exists and gives its number. The obligations — what you must do, must not build, must maintain, must pay — are in the instrument. This is the single most common reason a title search alone is not enough before buying or designing.
Can a Section 173 agreement be removed?
It can be ended or amended, but not unilaterally. The Act provides a process, and in the ordinary case it begins with the council: you apply, and the council decides. Where a council refuses or does not respond, the Act provides a further pathway. It is a legal process with a cost and a timeframe, not a form, and whether it is likely to succeed usually turns on whether the planning purpose the agreement was created for still exists.
Does it stop me building?
Only if it says so. Some agreements are administrative and never affect a project; others prohibit the exact thing you are planning. The only way to know is to read the agreement and compare it with what you intend — and it binds you independently of whether the planning scheme would permit the work.
Is it the same as a restrictive covenant?
No, although they can have similar effects. A covenant is usually a private restriction created on subdivision for the benefit of other lots. A Section 173 agreement is made with the council and exists for a planning purpose. They are created differently, read differently and ended through completely different processes.
I am buying. What should I do?
Order the agreement before you commit, not after. It is a modest cost against the purchase, and it is the document most likely to contain a surprise — the lot that cannot be subdivided again, the dwelling that cannot be rented separately, the obligation to maintain a system you did not know existed.