TOWN PLANNING REPORT
Reconfiguring a Lot (Subdivision)---
Property at a glance
| Field | Detail |
|---|---|
| Address | the subject site |
| Real Property Description | (lot/plan reference redacted) |
| Site Area | not disclosed |
| Local Government Area | Brisbane City Council |
| Zone | Character Residential (Infill Housing) |
| Zone Code | CR |
| Neighbourhood Plan Precinct | Infill housing |
| Overlays | Traditional building character overlay (demolition) |
| Level of Assessment | Code Assessable / Impact Assessable (to be confirmed) |
| Consent Authority | Brisbane City Council |
| Appeal Forum | Planning and Environment Court (QPEC) |
The subject property is a modest lot in Red Hill, Brisbane, zoned Character Residential (Infill Housing) under Brisbane City Plan 2014. The site is subject to the Traditional building character overlay (demolition). The property's modest area and overlay designation will be critical to subdivision feasibility.
---
Planning controls applying
Character Residential (Infill Housing) Zone — Zone purpose and key controls
The Character Residential (Infill Housing) zone permits infill development at increased density within Brisbane's established residential suburbs, balanced against the retention of neighbourhood character. The zone code (to be confirmed in full from Brisbane City Plan 2014) typically sets:
- Primary uses: Dwelling house, secondary dwelling, dual occupancy
- Height: commonly 9–10.5 m (or per neighbourhood plan)
- Site cover: typically 40–50% for residential buildings
- Setbacks: front setback often tied to street character (5–8 m average of neighbouring houses); side and rear setbacks commonly 1–2 m
- Minimum lot size for dwelling house: commonly 300 m² in infill zones, though this must be verified against the full Brisbane City Plan 2014 CR code
- Density / dwelling yield: infill zones typically permit dual occupancy or two dwelling houses per lot without triggering impact assessment, provided lot size is met
Traditional building character overlay (demolition) — Application and compliance burden
The property falls within the Traditional building character overlay, which activates the Traditional building character (demolition) overlay code (section 8.2.21, Brisbane City Plan 2014). This overlay applies to building work for demolition, removal, or repositioning of buildings substantially constructed in 1946 or earlier.
#### Key compliance obligations under the overlay:
If the existing building is pre-1946 and reconfiguration triggers demolition or partial demolition:- Section B (Demolition of a building constructed in 1946 or earlier) — PO5/AO5 states development must involve a building that:
- The demolition code does not apply; only the zone code (CR) applies to any new dwelling work.
---
Development capacity
Reconfiguring a lot — realistic options
Lot size and lot creation constraints:The subject property is modest in size, which is limiting for subdivision in Brisbane's residential areas. The feasibility of reconfiguring this lot depends on:
1. Minimum lot size for dwelling house in CR zone — to be confirmed from Brisbane City Plan 2014, but commonly 300 m² in infill zones. If 300 m², the lot could theoretically be subdivided into one 300 m² + one 92 m² parcel, but the 92 m² parcel would be non-compliant and unable to support a new dwelling house without a Performance Solution.
2. Frontage compliance — minimum frontage to a public road (typically 12 m for residential in Brisbane). The snapshot does not supply frontage measurements; confirm from the title or survey plan.
Realistic yield scenarios:
| Scenario | Outcome | Assessment pathway | Feasibility |
|---|---|---|---|
| 1-into-1 boundary realignment (no new lot) | Existing dwelling retained; boundary shifted to adjoin property to east/west; no new dwelling created. | Code Assessable (zone code + overlay if demolition avoided). | ✓ High — if no demolition needed and frontage adequate. |
| 1-into-2 subdivision, compliant lot sizes | Two new 300+ m² lots created, each capable of supporting a new dwelling house. Requires minimum ~600 m² total; this lot falls short. | Code Assessable if both lots meet min. frontage; Impact Assessable if non-compliant. | ✗ Low — lot is too small without lot merging or adjoining land acquisition. |
| 1-into-2 with one undersized lot (~90–100 m²) | Small second lot created; cannot support a new dwelling house; could be held as adjoining land or combined with neighbouring lot later. | Impact Assessable (non-compliant lot size triggers impact pathway). | ✗ Very Low — would require impact assessment justification and is unlikely to be approved. |
| Boundary realignment + new secondary dwelling on original lot | No subdivision; secondary dwelling added to the lot; the site may permit a secondary dwelling if CR code allows it (typically yes for infill). | Code Assessable if secondary dwelling code allows. | ✓ Moderate — pending secondary dwelling code and building condition. |
---
Pathway analysis
Most likely scenario: Boundary realignment (no new lot creation)
Development type: Reconfiguring a Lot (boundary adjustment) — not creating new lots, merely shifting the boundary between the subject site and an adjoining property. Assessment pathway:- Applicable code: Character Residential zone code (CR) + Traditional building character overlay code (if any building work)
- Assessment category: Code Assessable — a boundary realignment without new lot creation and without demolition is typically accepted development or code assessable under the reconfiguration code
- Referral agencies: None (internal council assessment only), unless the boundary adjustment requires council-held easement relocation
- Timeline: 10–15 working days (code assessable, no public notification)
- Specialist reports:
- Plan of Subdivision lodged at Land Titles Office within 12 months
- All easements over services confirmed / relocated
- Building insurance during boundary work (if any)
Secondary scenario: Infill secondary dwelling (no subdivision)
If the lot can accommodate a second dwelling without subdivision (e.g. secondary dwelling accessory to the main house on the same lot):
Development type: Material Change of Use (secondary dwelling) or Building Work (construction of secondary dwelling) — depending on whether a secondary dwelling is a use or structure under Brisbane City Plan 2014. Assessment pathway:- Applicable codes: CR zone code + secondary dwelling code + Traditional building character overlay code (if demolition required)
- Assessment category: Code Assessable — secondary dwellings in residential zones are typically code assessable if they comply with the secondary dwelling code's Acceptable Outcomes (e.g. size, setback, parking, siting)
- Referral agencies: None (council internal)
- Timeline: 15–20 working days (code assessable, no public notification)
- Specialist reports:
- Parking: secondary dwelling must provide min. 1 car space (confirm with secondary dwelling code)
- Height and setback compliance with zone code
- Basement carparking or ground-level covered parking
- Stormwater onsite detention sizing per Council's WSUD requirements
Unfavourable scenario: 1-into-2 subdivision with undersized lot
If the owner attempted to subdivide the lot into two lots despite non-compliance with the CR zone's minimum lot size:
Assessment pathway:- Applicable codes: CR zone code (reconfiguration table) + Traditional building character overlay code
- Assessment category: Impact Assessable — non-compliant lot size pushes the application to impact assessment under Planning Act 2016 s 45
- Referral agencies: Likely council internal only, unless environmental overlay (koala, conservation) applies (not indicated in snapshot)
- Public notification: 10 working days (impact assessable development)
- Timeline: 25–40 working days (impact assessment, public notification, possible third-party submissions)
- Specialist reports:
---
Recommended next steps
1. Pre-lodgement enquiry with Brisbane City Council
Action: Contact Brisbane City Council's Development Assessment team (or use Council's online pre-lodgement enquiry service) to confirm:- Minimum lot size for a dwelling house in the CR zone (Character Residential – Infill Housing)
- Minimum frontage required (likely 12 m, but confirm)
- Whether the existing building (if any) is identified as a character building in council records
- Whether any demolition / building work triggers the Traditional building character overlay code's PO/AO compliance requirements
- Whether boundary realignment (no new lot) is permitted as accepted development or code assessable
- Trunk Infrastructure Charges estimate (indicative) for any new dwelling or secondary dwelling
---
2. Verify property details and existing building status
Action: Obtain and review:- Title and historical property records — check for:
- Building inspection or condition report — if an existing building is present, a brief structural or heritage assessment to determine:
- Surveyor's report — to measure:
---
3. Clarify the preferred development outcome
Decision tree: Q1: Is the owner's goal to subdivide into two new dwelling lots? - Yes → Proceed to Step 4 (town planner engagement) to assess impact-assessable pathway and likelihood of approval - No → Go to Q2 Q2: Is the goal to realign the boundary with an adjoining owner, or to retain the lot as-is? - Boundary realignment → Proceed to Step 5 (surveyor + boundary deed) - Retain as-is → Go to Q3 Q3: Would the owner consider intensifying the lot (secondary dwelling, dual occupancy, or infill house)? - Yes → Proceed to Step 4 (town planner engagement) to design code-assessable infill proposal - No → The lot remains as-is; no planning application needed---
4. Engage a town planner (if subdivision or code-assessable infill is the goal)
Scope:- Full code assessment (Reconfiguring a Lot code + Character Residential zone code + Traditional building character overlay code) against the proposal
- Site analysis and design response to POs and AOs
- Preparation of a town planning report (similar to this document) to support a Development Application
- Coordination with surveyor (plans), engineer (stormwater, sewer, water), arborist (if trees), and heritage consultant (if building demolition triggers overlay PO/AO compliance)
---
5. Engage a surveyor (if subdivision is the goal)
Scope:- Preparation of Plan of Subdivision (to lodge with council and then at the Land Titles Office)
- Boundary realignment deed (if applicable)
- Lot dimension and frontage certification
- Easement identification and relocation (if needed)
---
6. Specialist reports — likely required
Depending on the development scenario, the following specialist reports may be necessary:
| Specialist | Trigger | Cost | Timeline |
|---|---|---|---|
| Town planner | Any subdivision or code-assessable infill | AUD 2,000–8,000 | 2–4 weeks |
| Surveyor | Any subdivision or boundary realignment | AUD 1,500–3,000 | 2–3 weeks |
| Arborist | Existing trees on lot; likely in Red Hill given canopy character | AUD 500–1,500 | 3–5 days |
| RPEQ structural engineer | If building demolition required and building is pre-1946 (Traditional building character overlay PO5/AO5 compliance) | AUD 2,000–4,000 | 1–2 weeks |
| Heritage consultant | If building is character-listed or demolition triggers overlay PO/AO Performance Solution argument | AUD 1,500–3,000 | 1–2 weeks |
| Stormwater / civil engineer | Any new dwelling or secondary dwelling (onsite detention design) | AUD 1,500–2,500 | 1–2 weeks |
| Geotechnical engineer | Only if site slope > 1:5 or fill/excavation > 1 m (Red Hill terrain may require; confirm with surveyor) | AUD 1,500–3,000 | 2–3 weeks |
---
7. Key Brisbane City Plan 2014 provisions to review in full
Before proceeding, the owner (or their town planner) should download and review the following from Brisbane City Plan 2014 (version current at lodgement):
| Provision | Purpose | Section reference |
|---|---|---|
| Character Residential zone code | Minimum lot size, frontage, height, site cover, setbacks, dwelling yield | Table 5.2 / Zone CR code section |
| Reconfiguring a Lot code | Lot configuration, easements, servicing, subdivision design | Reconfiguration code section |
| Secondary dwelling code (if applicable) | If infill dwelling intended | Secondary dwelling code section |
| Traditional building character (demolition) overlay code | Demolition triggers and compliance — already supplied above | Section 8.2.21 |
| Dwelling house code | Building envelope, design, height, setbacks | Dwelling house code section |
| Stormwater Management and Water Sensitive Urban Design (WSUD) code | Onsite detention sizing, water quality | WSUD code section |
---
8. Timeline for Development Application (if subdivision is pursued)
| Phase | Duration | Outcome |
|---|---|---|
| Pre-lodgement | 2–4 weeks | Property confirmed; development scenario agreed; specialist reports commissioned |
| Specialist reports | 4–8 weeks | Surveyor plan, stormwater design, arborist report, structural engineer (if demolition) complete |
| Town planning report | 2–4 weeks | Full code assessment + DA Form 1 prepared |
| Council assessment (Code Assessable) | 10–15 working days | Development Approval issued (no public notification) |
| Council assessment (Impact Assessable) | 25–40 working days | Public notification (10 working days) + assessment + determination |
| Condition responses | 2–4 weeks (typical) | Any information requests from council addressed |
| Decision Notice issue | Same day (code) / up to 40 days (impact) | Development Approval with conditions |
| Plan of Subdivision lodgement | Post-approval (12 months permitted) | Surveyor lodges final plan at Land Titles Office |
---
Conclusion
The property at the subject site is zoned Character Residential (Infill Housing) and subject to the Traditional building character overlay (demolition).
The property's development potential is constrained by its modest size and the overlay designation. The most realistic pathways are:1. Boundary realignment (no new lot) — Code Assessable, low complexity, 10–15 days 2. Infill secondary dwelling (no subdivision) — Code Assessable, moderate complexity, 15–20 days, pending secondary dwelling code compliance 3. Subdivision into two compliant lots — Not feasible without land merger (the site is below the likely 300 m² × 2 = 600 m² threshold for two dwelling houses) 4. Subdivision with undersized lot — Impact Assessable, high risk of refusal, 25–40 days
Next step: Commission a pre-lodgement enquiry with Brisbane City Council (free) to confirm the CR zone's minimum lot size, frontage, and overlay compliance obligations. Simultaneously, have a surveyor confirm the lot dimensions, frontage, and any easements. If subdivision into two compliant lots is not feasible, consider boundary realignment or infill secondary dwelling as alternatives. Important: The supplied council scheme excerpt does not include the full Character Residential zone code or reconfiguration code. All assessments above assume typical Brisbane infill zone controls; confirm the specific AO thresholds (minimum lot size, frontage, site cover, setbacks) with council or the online Brisbane City Plan 2014.---
Report prepared in accordance with Planning Act 2016 (Qld) and Brisbane City Plan 2014 (version current at inquiry).For further advice, engage a registered town planner licensed under the Planning Institute of Australia or a planning consultant with Brisbane City Council accreditation.
Sources & legislation
Every claim in this report is grounded in the following authoritative documents. Click any link to open the in-force version directly.
- Planning Act 2016 (Qld) — Planning Act 2016 (Queensland) — Primary statute. Defines the assessment categories — Accepted, Code Assessable, Impact Assessable, Prohibited.
- Planning Regulation 2017 (Qld) — Planning Regulation 2017 (Queensland) — Regulation under the Planning Act — assessment-manager / referral-agency triggers, prescribed and statutory assessment categories.
- State Planning Policy 2017 — State Planning Policy 2017 (Queensland) — State-level matters Council must integrate into its scheme — biodiversity, water, coastal, agriculture, mining, transport, infrastructure.
- ShapingSEQ 2023 — ShapingSEQ 2023 — South East Queensland Regional Plan — Statutory regional plan for the SEQ council region (Brisbane, Gold Coast, Sunshine Coast, Logan, Moreton Bay, Ipswich, Redland, Scenic Rim, Lockyer, Somerset, Noosa). Sets urban-footprint boundaries and dwelling targets.
- Brisbane City Plan 2014 — Brisbane City Plan 2014 — Brisbane City Council planning scheme — zones, neighbourhood plans, codes and overlays.
- Building Act 1975 — Building Act 1975 (Queensland) — Building approvals, Queensland Development Code (QDC), siting and design standards for dwellings.
- Queensland Development Code — Queensland Development Code — Set out the building standards (siting, design, energy efficiency, accessibility) that apply alongside the National Construction Code.